What is a Sustainable Management Plan (SMP)?

A Sustainable Management Plan (SMP) is a report based on the Built Environment Sustainability Scorecard (BESS). It aims to assist councils and developers in achieving sustainable developments.

Currently, 35 local councils in Victoria utilise the scorecard. The following nine sections are required to show various levels of compliance to pass:

  • Management
  • Water
  • Energy
  • Stormwater
  • Indoor Environmental Quality
  • Transport
  • Waste
  • Urban Ecology
  • Innovation

Depending on the proposed development, there will be different criteria to satisfy each section. For example, an apartment building will have different requirements than a commercial office building.

On top of the BESS scorecard, preliminary thermal modelling (energy rating reports or section J calculations) and STORM treatment calculations will also be provided.

Why is a Sustainable Management Plan (SMP) needed?

A Sustainable Design Assessment is a report requested by councils that utilise an ESD policy. Depending on the council, they will be triggered once nine (9) or more dwellings or a commercial development building of more than 2000 square meters are proposed.

As we build more buildings in tighter spaces, councils want to ensure we build more sustainably while reducing our carbon footprint.

Some of the key takeaways from the councils’ ESD policies are:

  • Reduction of costs over the life of the building
  • Improved affordability over the longer term through reduced running costs
  • Improved amenities and livability
  • More environmentally sustainable urban forms
  • Integrated water management
Passive Energy 0006 Smp 1
Smp 1

Why you need a trained BESS professional for your SMP

While it is a simple scorecard system to use, a trained BESS professional can ensure best practice initiatives are selected for each section. Every council has preferred sustainable initiatives they want to implement, even at different levels of compliance.

A BESS-trained professional will know how to prepare the STORM calculations correctly, per the specific council requirements and prepare preliminary thermal modelling. Issues can arise and be sorted in the design and planning stage to avoid expensive building costs later.

How do we prepare a Sustainable Management Plan (SMP)?

We prepare our Sustainable Management Plan for you following the nine criteria of the BESS Scorecard.

Management

Points are awarded for providing:

  • Attending council meetings as an ESD consultant
  • Preliminary thermal modelling
  • Independent energy and watering metering
  • A building user guide

It is important to ensure the consultant who prepares your Sustainable Management Plan conducts preliminary thermal modelling, especially energy ratings for townhouses and apartment buildings.

Water

Points are awarded for providing:

  • Water tanks
  • Energy efficiency water fixtures
  • Efficient landscaping

The water tanks are essential for new developments and they serve two purposes:

  • They assist with water reuse: When the land is originally developed and subdivided, the underground assets are usually calculated with the intention of building one dwelling per site. As time goes by, old homes are demolished, and multiple dwellings are built on each site, we put strain on the existing main water supply. Rainwater tanks help with the water supply for toilet flushing, watering your garden and laundry washing.
  • They act as a detention system: Heavy rainfalls can be difficult for underground water systems to cope with, especially when you add dwellings. More dwellings mean more rainwater connected and more downpipes sending water back underground. Rainwater tanks collect and hold this water for reuse and only send it back to the legal point of discharge once the water reaches the overflow pipe.

Note: You will need to achieve a minimum of 50% to pass the Water section of the BESS scorecard.

Energy

Points are awarded for providing:

  • Preliminary thermal modelling results
  • Solar panels
  • Efficient appliances
  • Reduced artificial lighting reliance

As per the management section that acknowledges preliminary thermal modelling will be conducted, the energy section is where the results are incorporated. Achieving a higher star rating will improve the energy section results.

We have been able to offer cost-saving advice on dwellings that did not initially perform well. If these were not picked up in the design stage, the developer would have been up for expensive windows once the building permit energy ratings were prepared. It is too late then to make changes to the design and possibly have to advertise to the council.

Whoever prepares your Sustainable Design Assessment, please ensure that preliminary energy ratings are conducted and request the window values.

Note: You will need to achieve a minimum of 50% to pass the Energy section of the BESS scorecard.

StormWater

Points are awarded for providing a STORM calculation of 100% or more.

Melbourne Water has developed the STORM (Stormwater Treatment Objective - Relative Measure) calculator to assess how stormwater is collected and treated before entering back into the underground pipes.

The main treatment types we nominate to demonstrate compliance are:

  • Rainwater tanks
  • Rain gardens
  • Buffer strips
  • Permeable paving

What we nominate depends on the council and their preferred treatment types. Some councils will not allow rain gardens in dwellings and some will not allow them for common space.

We do hundreds of STORM scorecards every year so we know what each council prefers to ensure that yours is approved at the first round of applications.

Note: You will need to achieve a minimum of 100% to pass the Stormwater section of the BESS scorecard.

Indoor Environmental Quality (IEQ)

Points are awarded for providing:

  • Double glazing to all habitable rooms
  • Open windows that allow for cross-ventilation
  • Design at least 50% of the dwellings to have north-facing living
  • Good daylight access
  • Appropriate shading devices depending on the orientation

This section ensures the building designer or architect has utilised good passive design principles in the design and that good natural lights and comfort are achieved for the building occupants.

Note: You will need to achieve a minimum of 50% to pass the Indoor Air Quality section of the BESS scorecard.

Transport

Points are awarded for providing:

  • A bike rack for each dwelling and a visitor bike rack for each group of five dwellings
  • Showers for bike riders (Commercial developments)
  • EV charging stations
  • Car share scheme
  • Parking spaces for motorbikes and mopeds

You need to ensure that enough space is allocated for bikes for residential developments and alternative transport options for commercial developments.

We will also provide the council with a walk score and basic transit information for the development.

Note: There is no minimum pass mark to achieve compliance for Transport, however, the results go towards obtaining the minimum 50% BESS scorecard to meet BESS best practice compliance.

Waste

Points are awarded for providing:

  • Recycled building material for demolished building works
  • Appropriate rood and garden waste management
  • Convenient recycling management

If there is an opportunity to recycle building waste, prepare documentation for the council.

Note: There is no minimum pass mark to achieve compliance for Waste, however, the results go towards obtaining the minimum 50% BESS scorecard to meet BESS best practice compliance.

Urban Ecology

Points are awarded for providing:

  • Large areas of vegetation
  • Green roofs
  • Green walls
  • Taps to balconies
  • Dedicated food production areas

The more green, the more points. Ensure that the development has at least 35% of the vegetation area allocated.

Note: There is no minimum pass mark to achieve compliance for Urban Ecology, however, the results go towards obtaining the minimum 50% BESS scorecard to meet BESS best practice compliance.

Innovation

Points are awarded for providing innovative technology or initiatives not included within BESS.

Generally, we reserve these points for large development projects. We will need to achieve 50% before we can start claiming innovation points.

As some developments require higher scores than 50% to satisfy council ESD requirements, we can use these initiatives to earn additional points not currently found within the BESS scorecard.

What we need from you to prepare a Sustainable Management Plan (SMP)

To prepare a Sustainable Management Plan, we will need town planning drawings with the following information:

  • Site Plan with neighbouring information
  • Floor plan with one overall dimension
  • Elevations with cladding details and window opening style
  • Site analysis areas

Any council request for further information letter or planning permit will also be helpful.

At the end of the process, you will get the following documents and information from us:

  • Detailed specifications for each BESS section
  • BESS Scorecard modelling
  • STORM Scorecard modelling
  • Preliminary energy rating (For Residential)
  • Preliminary section J insulation and glazing (For Commercial)
  • Walkscore information
  • PDF documents for STORM treatment types
  • ESD notes for your planning drawings
Google Reviews
Google
Jackson T profile picture
Jackson T
May 25, 2023
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Best energy assessor's I've ever worked with. These guys have great communication, fast turn arounds and are always super helpful when requesting feedback on a design proposal.
Google
Nor Eltaha profile picture
Nor Eltaha
May 24, 2023
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Rob from PassivEnergy managed to achieve a 7 star energy rating for my home by offering some design tips. Communication and service was excellent. Highly recommended.
Google
Nikolaos Tzovaras profile picture
Nikolaos Tzovaras
May 23, 2023
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
PassivEnergy has been my go-to thermal performance assessing company, and their service has been consistently exceptional. Their expert team's deep knowledge and commitment to staying ahead of advancements in the field have significantly influenced the success of my building designs. Their personalised approach, professionalism, and timely delivery have made them an invaluable partner. I highly recommend PassivEnergy for their outstanding service and dedication to sustainable outcomes.
Google
Roman Z profile picture
Roman Z
October 3, 2022
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
I have used the team at PassivEnergy for a few of my townhouse developments over the last couple of years. Their knowledge on the preferred preference of the individual councils I have developed in has been impressive and the tips they provided in the design layout meant I was able to save on window glazing. Thanks team, see you on the next development.
Google
Stacey Pierce profile picture
Stacey Pierce
July 1, 2022
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
Thank you Rob for your fantastic advise and knowledge. Your communication, customer service and turn around time exceed our expectations by far. We highly recommend Rob at PassivEnergy. Thank you very much.
Google
Michael Woolfe profile picture
Michael Woolfe
December 22, 2020
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
I recently dealt with Rob from Passive energy to seek some assistance with existing north facing windows adjacent to a proposed garage. Rob’s vast knowledge of the current building regulations and energy requirements made ease of understanding a tricky situation. Rob’s professionalism and efficient turnaround time to provide a solution enabled the project to keep moving forward. I would highly recommend PASSIVENERGY services for all energy performance requirements for proposed & existing dwellings. A+ service
Google
Jane RD profile picture
Jane RD
May 26, 2020
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
We have been dealing with Rob and PassivEnergy for a number of years now and couldn’t speak more highly of them. They have great service and turnaround times and we’ve never had a problem while working with PassivEnergy on our projects. They are always helpful with any questions or revisions and offer solutions for those tricky situations. Rob and the team are our first port of call for energy assessments or WSUD reports. We look forward to working with the team for a long time to come. - On behalf of the team at Lateral Building Design.
Google
Kristie Nevill profile picture
Kristie Nevill
December 7, 2017
Google star 1Google star 2Google star 3Google star 4Google star 5Trustindex verifies that the original source of the review is Google.
I found PassivEnergy via a Google search knowing nothing other than that I required an energy report for my building permit application. Rob was quick at getting back to me with a quote and very reasonably priced in comparison to his competitors. The report was detailed and he worked closely with us to answer all the questions we had. The report was delivered in the promised timeframe and the customer service was exceptional. I cannot recommend Rob and PassivEnergy more highly!

Our fast & efficient process

Getting a 6 Star Energy Rating does not need to be timely, confusing or expensive.

Infinity. Passive Energywebp

See our work

Contact us and we will guide you through the process of completing your Sustainable Management Plan.

Get a quote

Name(Required)
Drop files here or
Accepted file types: jpg, pdf, ai, png, doc, docx, xls, xlsx, Max. file size: 40 MB, Max. files: 4.

    FAQs

    What's involved with the SMP analysis?
    How can we improve the results of the BESS report?
    When is the best time to do a Sustainable Management Plan?